Customer wants a dropdown to be able to mark document as reviewed. I have the dropdown default to No and the validate expression says it must be Yes.
After the validation is cleared, everything looks good...
BUT...I can't complete the task.
If I stop the Data Review Session and go back in THEN I can complete the task.
Tagged:
0
Comments
Only when a user commits field value changes, does the Attended Client evaluate the complete status. Field changes are committed when a user navigates to another document, closes the current task or clicks 'Save'.